Sunrise Dam Power Station Upgrade 8

  • Energy
  • Laverton, Western Australia
  • Qetra Scope $3.5m+
  • October 2021 – December 2022

Project Summary


Sunrise Dam is a gold mine located near Laverton in Western Australia. The mine and nearby village are powered by a diesel/gas hybrid power station.

Expansion 8 required the upgrade of the existing station D to increase capacity by adding a new 4MW CAT engine, piping, ventilation, cooling and exhaust. A new Switchroom was installed, along with transmission lines and buried services.

Qetra was contracted to complete the entire scope of the project from offsite fabrication and assembly, through to on site installation, including during shutdowns and cutovers, and complete commissioning works.

Qetra’s scope of work included:

  • Civils – Excavation, buried services, concrete and precast
  • Structural – Fabrication and installation
  • Mechanical – Pumps, radiators and engine
  • Piping – Fabrication and installation of gas, water and oil piping
  • HV – Installation and terminations
  • Transmission lines – Cutover to existing
  • Heavy lift – Switchroom & engine installation
  • Commissioning
Privacy Settings
We use cookies to enhance your experience while using our website. If you are using our Services via a browser you can restrict, block or remove cookies through your web browser settings. We also use content and scripts from third parties that may use tracking technologies. You can selectively provide your consent below to allow such third party embeds. For complete information about the cookies we use, data we collect and how we process them, please check our Privacy Policy
Youtube
Consent to display content from - Youtube
Vimeo
Consent to display content from - Vimeo
Google Maps
Consent to display content from - Google
Spotify
Consent to display content from - Spotify
Sound Cloud
Consent to display content from - Sound